Twin Peaks Interchange postponed
Posted: Thursday, Mar 19th, 2009
By Chuck Barth
MARANA — The lack of a timely deposit has put the Twin Peaks Interchange program on hold for at least a month.
According to a letter from Marana Town Manager Gilbert Davidson to the Executive Director of the Pima Association of Governments/Regional Transportation Authority (RTA) Gary Hayes, the RTA failed to make a $15 million deposit into a local government investment pool (LGIP) account with the state.
The deposit failure caused the Arizona Department of Transportation (ADOT) to delay the awarding of the contract.
Bids were opened last month and the project came in under budget.