- The Design Concept and Environmental Assessment was completed in late 2005.
- The Final Design is underway and is anticipated to be complete in early 2008.
- A public meeting was held in June 2007 to review the status of the new interchange, for more information visit the Public Outreach page.
- The Project is anticipated to go to bid in mid-2008, construction to begin shortly after.
- The new interchange will open to traffic in early 2010, with aesthetic and landscape treatments continuing throughout the year.
|
|